Do I Need a New Meter for Solar? How Utilities Handle Net Meters

Do I Need a New Meter for Solar? How Utilities Handle Net Meters

Before solar can run, your utility usually installs or reprograms a meter that measures power both ways. Here is how it works and what it costs.

Most homes need a new meter for solar, or at least a reprogrammed one, so the utility can measure electricity flowing both into and out of the house. Your utility handles this after it approves your system, usually just before permission to operate; Southern California Edison, for example, says customers with a smart meter already meet the requirement but still need the meter programmed, while other utilities install a new bi-directional meter.

Key takeaways

  • A solar home needs a meter that records both the amount and the direction of power flow.
  • Your utility installs or reprograms the meter; never open or tamper with the meter or meter socket yourself.
  • Some utilities charge nothing for the change; others charge application or meter fees.
  • Do not run a grid-tied system until the meter work is finished and the utility gives permission to operate.

Why solar needs a different meter

A standard meter only needs to count the electricity you buy. Once solar panels are connected, your home sometimes sends extra power to the grid. Under net metering or net billing, the utility needs to measure both directions so it can credit your exports.

Florida Power & Light puts it simply in its net metering FAQ: once your application is approved, it installs a meter that measures both the quantity and the direction of electricity flow. Dominion Energy Virginia calls it a bi-directional meter. Either way, the result is a bill that shows energy delivered to you and energy you sent back. Dominion's page also notes that the solar system must be interconnected on the customer's side of the utility's metering equipment, so the meter sits between your home and the grid and sees the net flow. Our guide to net metering explains how those credits work.

Do I need a new meter for solar if I already have a smart meter?

Often not a new one, but it still needs work. Southern California Edison's net energy metering FAQ says:

  • If your current meter is not compatible, SCE will replace or reprogram it as part of enrollment.
  • Customers with a smart meter already meet the requirement, but SCE must still program the meter.
  • Meter reprogramming is handled by SCE and your contractor, and it must happen before you can operate the system.

Other utilities swap the meter regardless. Dominion Energy Virginia says a bi-directional meter will be installed once contingent approval is granted. Benton PUD in Washington schedules a bi-directional meter on the main service after inspections. The only way to know is to ask your utility or read its interconnection page.

What a new meter for solar costs

Costs vary from nothing to a few hundred dollars, depending on the utility. These examples come from each utility's own pages, checked in November 2026.

UtilityWhat it does with the meterFees mentioned on its page
Florida Power & LightInstalls a meter that measures quantity and direction after approvalNo meter cost stated; application fee for larger Tier 2 and Tier 3 systems; $30 minimum base bill (not a meter fee)
Dominion Energy VirginiaInstalls a bi-directional meter after contingent approval"Often there are no charges" for interconnecting small residential systems
Southern California EdisonReprograms smart meters or replaces incompatible metersNo general meter cost stated; storage output meters capped at $600 for most projects
Benton PUD (Washington)Installs a bi-directional meter plus a production meter on the solar system$100 application fee; $350 net meter fee toward the production meter; $150 re-inspection fee

Your installer's quote should say whether any utility fees are included. If it does not, ask. Our article on utility interconnection fees for solar covers other charges you may see.

Production meters and other equipment near the meter

Some utilities want a second meter that measures only what the panels produce. Benton PUD, for example, installs a production meter on the solar system in addition to the bi-directional meter on the main service.

Other equipment can end up near the meter too:

  • Disconnect switches: FPL requires a manual disconnect switch next to the meter socket for its Tier 2 and Tier 3 systems.
  • Storage meters: SCE mentions a net generation output meter (NGOM) for some storage projects and says NGOM pricing for most projects is capped at $600.
  • Metering cabinets: Dominion says a system may not be connected inside the metering cabinet without its prior approval.

If your main electrical panel lacks room for a solar breaker, the installer may propose a panel upgrade or a different connection method. See our guide to the 120% rule for solar for why.

When the meter is installed: the timeline

The meter change is one of the last steps. A typical order, based on the utility pages above, looks like this:

  1. Submit the interconnection application and get approval.
  2. Install the system after any required preapproval.
  3. Pass local inspections and submit the completion paperwork to the utility.
  4. The utility installs or reprograms the meter.
  5. The utility issues permission to operate.

Timing varies. SCE says it issues permission to operate for most standard projects within 10 business days of receiving a complete package, and that if a meter change is needed it arranges installation before PTO. It also notes that net metering billing setup can take a few billing cycles. Benton PUD schedules its meter installation after receiving the certificate of completion following both inspections.

How the meter fits with permits, inspections and roof work

The utility will not touch the meter until the local inspections are done. Each utility sets its own paperwork, but the pattern is similar:

  • Dominion Energy Virginia requires certification by a licensed Virginia electrician and/or a local inspection before the final step in its portal and permission to operate.
  • Benton PUD asks for an electrical schematic and verification that the inverter is UL 1741 listed with the application, and schedules the meter only after inspections by both the utility and Washington State Labor & Industries.
  • SCE says that for system expansions, customers should not operate added equipment until a new permission to operate is issued.

Roof decisions rarely affect the meter itself, but they affect when you reach the meter step. A roof that needs replacing, a structural fix or a failed inspection all push the meter change later.

If your installer closes before the meter work is finished, you may still be able to complete the process with the utility and a new licensed contractor. Our guide to getting permission to operate if your installer disappeared walks through those steps.

Checks after the meter is changed

  • Confirm you received written permission to operate before switching the system on.
  • Ask your utility how to read the delivered and received values on your meter display.
  • Check your next bills for a net metering or solar rate code and an export line.
  • Compare the export reading with your inverter app over the same days.
  • If exports do not appear after a couple of billing cycles, call the utility and your installer.

Keep your first few bills after the change so you can spot a missing export credit early.

Next steps

Look up your utility's net metering or interconnection page and note any meter fees. Then estimate how much of your power you would export with our solar panel calculator, and check typical system data for your state on our solar panels pages.

Frequently asked questions

Does the utility change my meter when I get solar?

Usually yes, or it reprograms the existing smart meter. Utilities such as Dominion Energy Virginia install a bi-directional meter, while SCE reprograms compatible smart meters.

Do I have to pay for a new solar meter?

It depends on the utility. Dominion Energy Virginia says there are often no charges for interconnecting small residential systems, while others, such as Benton PUD in Washington, charge application and meter fees.

Can I turn on my solar panels before the meter is changed?

No. Utilities require the meter work and permission to operate before you run a grid-tied system.

What is a bi-directional meter?

It is a utility meter that measures both the electricity you draw from the grid and the electricity your system sends back, so the utility can bill and credit you correctly.

What is a solar production meter?

It is a separate meter that records only what your solar system produces. Some utilities require one in addition to the main bi-directional meter.

Sources

Related guides

Questions and comments

Be the first to ask a question or share your experience.

Comments are checked before they appear. No links or advertising. Guidelines.

Calculators for this topic

More solar guides

All solar guides →