Steps to Go Solar: From First Quote to Permission to Operate

Steps to Go Solar: From First Quote to Permission to Operate

A step-by-step map of going solar, from reviewing your bills and comparing quotes to permits, inspection and the utility's permission to operate.

The steps to go solar are: check your usage and roof, collect and compare bids, sign a contract, let the installer pull permits, install the system, pass the local inspection, and then wait for your utility's permission to operate (PTO) before switching it on. Installation itself usually takes only days; DOE notes that permits and inspections can take weeks to months.

Knowing the order helps you spot delays, ask the right questions and avoid turning the system on too early. Here is each step in plain English.

Key takeaways

  • Most of the calendar time goes to paperwork: permits, inspections and utility approval.
  • Get at least three bids that describe the same kind of system so you can compare them.
  • Door-to-door and in-home sales may come with a federal three-day right to cancel.
  • Do not turn the system on until your utility gives written permission to operate.
  • The federal 25D credit is not allowed for expenditures made after December 31, 2025, which for solar means installations completed after that date.

Overview: the steps to go solar at a glance

StepWho leads itWhat you get at the end
1. Usage and efficiency reviewYou12 months of kWh use and a list of planned changes
2. Site and roof checkYou and installersA sense of shade, roof age and HOA rules
3. Bids and comparisonYouThree or more written quotes
4. Financing and contractYou and the installer or lenderA signed contract you fully understand
5. Design, permits and interconnection applicationInstallerApproved building permit; utility application filed
6. InstallationInstallerPanels, inverter and wiring in place
7. Local inspectionCity or county inspectorFinal building permit sign-off
8. Utility review and PTOUtilityWritten permission to operate and, often, a new or reprogrammed meter

Before the first quote: steps 1 and 2

Step 1: Review your usage and cut waste

DOE's Energy Saver suggests starting with energy efficiency, such as an energy audit, efficient appliances, LED lighting and weatherizing, because a smaller need means a smaller system. Then pull a year of bills and note your monthly kilowatt-hours (kWh), including seasonal swings. Add anything you plan, like an electric vehicle or a home addition.

Step 2: Check your roof and site

DOE suggests having a solar installer, roofing expert or structural engineer assess your roof, and checking local permit records if you do not know its age. If the roof needs replacing within a few years, it can save money to do that at the same time. Also look at shade from trees and any HOA rules. Online mapping tools are a starting point, but DOE notes they do not account for every variable.

Comparing quotes and signing: steps 3 and 4

Step 3: Get and compare bids

DOE recommends at least three bids based on the same characteristics. DOE says each should state the system's maximum generating capacity in watts or kilowatts and the total cost of getting it running, including hardware, installation, grid connection, permitting, sales tax and warranty. DOE says cost per watt and estimated cost per kWh are the most useful numbers for comparing installers. The FTC adds that bids should show how much power the system is expected to deliver, whether any output is guaranteed and which warranties apply to the equipment.

Check each installer's license and complaint history. Our solar company directory is one place to start, and our solar quote checker helps you see whether a price is in a normal range.

Step 4: Choose financing and sign

Options include cash, a loan, a lease, a power purchase agreement or community solar. The FTC suggests asking lenders about APR, payment changes, balloon payments and liens, and checking whether a lease can be transferred if you sell your home.

If you sign at home or at a temporary sales location, the FTC's Cooling-Off Rule may give you until midnight of the third business day after the sale to cancel for a full refund (Saturday counts as a business day; Sunday and federal holidays do not). Sales under $25 at home or under $130 at temporary locations are not covered, and many states have their own rules too.

On taxes: the IRS says the Section 25D credit is not allowed for expenditures made after December 31, 2025, and the expenditure is treated as made when installation is completed. Be skeptical of any pitch that still promises it for a new system.

Permits and installation: steps 5 and 6

Once you sign, the installer finalizes the design, applies for local building and electrical permits, and usually files the utility interconnection application. DOE notes the installer typically handles permits and inspections. NLR (formerly NREL) research shows that review processes are spread across roughly 20,000 jurisdictions and 3,000 utilities, which is why timelines vary so much. Where a city uses the automated SolarAPP+ tool, NLR found permit review times dropped from as many as 20 business days to zero.

The physical installation is the short part. PG&E tells customers it generally takes a few days to a few weeks, and DOE describes it as generally only a few days.

Inspection and permission to operate: steps 7 and 8

After installation, the local building department inspects the work for safety and code compliance. PG&E, for example, requires a copy of the final building permit or inspection certificate before it will finish its review. The utility may then do an engineering review, update your meter and send written permission to operate. PG&E says this typically takes 5 to 10 business days after it receives the paperwork, with a maximum of 30 business days.

The rule that matters most: PG&E says never to turn on the system before receiving permission to operate. Other utilities have similar rules; Loveland Water and Power in Colorado, for instance, issues PTO only after final inspections, system validation and the interconnection agreement are complete. Our full guide to permission to operate explains what to do if it stalls.

A few utility details can add time. PG&E notes that its engineering review may find grid upgrades are needed, which can add cost and delay. PG&E tells contractors that customers without a smart meter need an inspection before PTO so a net metering meter can be installed. Most PG&E customers do not get an on-site utility inspection, but some applications are picked at random for a post-installation check. Including your email address on the application can speed up delivery of the PTO letter.

Common mistakes in the steps to go solar

  • Comparing quotes that describe different systems. Line up size, panels, inverter and warranties before comparing price.
  • Signing on the first visit. The FTC warns against companies that pressure you for a quick decision or ask you to pay in cash.
  • Skipping the roof check. Removing panels later to replace a roof adds cost.
  • Turning the system on early. Operating before PTO can break utility rules.
  • Not keeping copies. Save the contract, permit, inspection sign-off, interconnection agreement and PTO letter. You will need them for warranty claims and when you sell.

Questions to ask your installer about the process

  • Who files the permits and the utility application, and when?
  • What is your typical time from signing to PTO in my town and with my utility?
  • Will my utility need to upgrade anything, and who pays if it does?
  • When does my first loan or lease payment start: at install or at PTO?
  • Will you show me how to turn the system on after PTO and set up monitoring?

Next steps

Begin with step 1: estimate your system size with our solar panel calculator using your last 12 months of bills. Then gather bids, compare them carefully, and check each one with the quote checker before you sign. For more on the inspection stage, see solar permits and inspections explained.

Frequently asked questions

How long does it take to go solar from start to finish?

It varies widely by town and utility. DOE notes installation usually takes only a few days, while permits and inspections can take weeks to months, and the utility's approval comes after that.

Can I turn on my solar panels before permission to operate?

You should not. PG&E, for example, tells customers never to turn on a system before receiving permission to operate, and other utilities have similar rules.

Who applies for solar permits, the homeowner or the installer?

Usually the installer. DOE says your installer typically handles local permits and inspections, and the installer often files the utility interconnection application too.

Can I cancel a solar contract after signing?

If you signed at home or at a temporary location, the FTC Cooling-Off Rule may let you cancel until midnight of the third business day after the sale. Check your contract and state law for any additional rights.

How many solar quotes should I get?

DOE recommends at least three bids based on the same characteristics, compared on cost per watt and estimated cost per kWh.

Sources

Related guides

Questions and comments