Incentives & Policy

Net metering in Maryland: how solar credits work, and what changes in July 2027

Net metering in Maryland: how solar credits work, and what changes in July 2027

Maryland credits solar exports one for one and pays leftovers each April, but new enrollment ends July 1, 2027. Here is how it works by utility.

Net metering in Maryland lets a solar home bank the electricity it sends to the grid as kilowatt-hour credits that offset later usage. Leftover credits either pay out once a year, at the end of a 12-month period that closes in April, at the generation (commodity) rate, or roll forward indefinitely if you choose. As of November 2026, the program still accepts new systems, but under a 2026 state law it closes to newcomers on July 1, 2027, or sooner if 3,000 MW is reached, when a successor program takes over.

Key takeaways

  • Maryland nets your solar exports against your usage, and unused kWh credits carry forward to later bills.
  • Leftover credits are paid once a year after the 12-month period ending in April, valued at the generation portion of your rate averaged over 12 months. Since October 1, 2023 you can instead accrue them indefinitely.
  • Systems can be sized up to 200% of your annual baseline use and up to 2 MW.
  • The Utility RELIEF Act of 2026 ends new enrollment on July 1, 2027, or at 3,000 MW if sooner. Customers under a net metering contract on that date stay on it until they repower, expand, sign a new interconnection agreement or decommission.
  • The PSC must approve a successor program by February 1, 2027. The working group's draft framework was due October 27, 2026.

How net metering works in Maryland

Your meter measures electricity in both directions. During a billing period, usually a month, the utility measures what you pulled from the grid and what your panels pushed back, and you are billed for the net amount. Check your utility's net metering rider for how fixed charges on your bill are handled.

When your panels produce more than you use in a month, the extra is not lost. It becomes a kWh credit that carries into the next bill. In practice, summer surplus can cover part of your winter usage.

A few ground rules from the PSC's 2025 net metering report:

  • A net-metered system can be up to 2 MW (community solar systems up to 5 MW).
  • It may be sized to produce up to 200% of your annual baseline electricity use.
  • The statewide limit on eligible capacity is 3,000 MW.

What happens to excess credits: April payout or indefinite rollover

Maryland gives you two choices for credits you have not used.

Option 1: Annual payout

Your credits accumulate over a 12-month period that ends with the billing cycle just before the end of April. The utility then pays you for any balance left, within 30 days. The PSC says the dollar value equals the generation or commodity portion of the rate the utility would have charged, averaged over the previous 12 months, times the leftover kWh. That rate is lower than the full retail price you pay per kWh because it leaves out delivery charges. In the 12 months ending April 30, 2025, Maryland utilities paid about $5.15 million to residential customers for excess generation.

Option 2: Accrue indefinitely

Under SB 143, effective October 1, 2023, you can choose to carry credits forward with no annual payout. This makes sense if you expect your usage to rise, for example after buying an electric vehicle or a heat pump. A credit used against a future bill is worth your full per-kWh rate, while a cashed-out credit is worth only the supply portion.

FirstEnergy, the parent company of Potomac Edison, shows how this works in practice. Customers already on its net meter rider stay on the 12-month method unless they ask to change. You can switch no more than once per calendar year. To avoid the next April payout, you must request the indefinite method by December 31. Under the indefinite method, credits are paid out only if you switch back or close your account. Other utilities' election forms may differ, so ask yours.

Net metering rules by Maryland utility

Net metering is set by state law and PSC regulations, so the core rules are the same across utilities. What differs is the paperwork, the supply rate used for payouts, and how many customers are on each system. Here is how the larger utilities compare as of the PSC's June 30, 2025 data.

UtilityNet-metered capacity (kW, June 30, 2025)Residential excess-generation payouts (12 months to April 30, 2025)
BGE563,855$1,932,727.94
Pepco360,042$2,242,246.30
Potomac Edison139,880$270,333.86
Delmarva Power128,179$380,404.18
SMECO (co-op)90,310$213,578.42
Choptank Electric (co-op)34,057$105,564.62
Statewide total1,321,097$5,148,988.71

Smaller utilities, including Easton Utilities and the municipal systems in Berlin, Hagerstown, Thurmont and Williamsport, also report net-metered customers to the PSC. Whichever utility serves you, ask for its net metering rider and its excess generation election form before your system goes live, so you can pick the payout option you want.

The 2027 net metering deadline in Maryland

This is the biggest change for anyone shopping for solar now. The Utility RELIEF Act (House Bill 1532, Chapter 353 of 2026) rewrites Public Utilities Article § 7-306.

  • End of new enrollment. The standard net metering contract stays available until the earlier of 3,000 MW statewide or July 1, 2027.
  • Successor program. Under new § 7-306.4, the PSC must approve a framework for a successor program by February 1, 2027. That program begins July 1, 2027, and stays open until combined capacity under both programs reaches 6,000 MW.
  • Grandfathering. A customer under a net metering contract on July 1, 2027 stays eligible until the earliest of decommissioning, adding modules or AC capacity, signing a new interconnection agreement, or repowering (replacing more than 80% of the module capacity; routine repairs and storm repairs do not count).
  • Queue priority. The PSC must prioritize successor program applications from customers already in a utility's interconnection queue for the existing program.

The PSC opened Public Conference 78 on May 14, 2026 to design the successor and named a working group, which was due to file a draft report and framework by October 27, 2026. As of early November 2026, no successor credit value had been approved.

A second open question is which milestone a new system must reach by July 1, 2027 to keep net metering. The PSC's proposed regulations (rulemaking RM 56) list three versions: an interconnection application submitted by that date, permission to operate by that date, or a signed net metering interconnection agreement by that date. Under the third version, a customer who applied but had not signed an agreement would move to the successor program with priority review. We found no final decision as of early November 2026. Successor credits are widely expected to be lower, but no rate has been set, so be cautious of any installer who quotes one.

Portable solar is separate

The same law also addresses small portable (plug-in) solar systems: no more than one per electric meter, limited to 1,200 watts of output back to the home's wiring. These are a separate category from a rooftop net-metered system, so ask your utility how it treats them before you count on any bill credit.

How Maryland net metering affects payback

Under today's rules, a kWh your panels send to the grid offsets a kWh you would otherwise have bought, as long as you use the credit on a later bill. That is the most valuable form of net metering a homeowner can get. Payback then depends mainly on system cost, how much sun your roof gets and your rate per kWh.

Three practical points:

  1. Size for use, not maximum payout. Annual cash-outs are paid at the lower supply rate, so a system far larger than your needs earns less on the extra output.
  2. Pick indefinite accrual if usage will grow. Credits you bank now can cover a future EV or heat pump at full value.
  3. Mind the calendar. A system that misses grandfathering will be valued under the successor program, which could lengthen payback.

You can check current Maryland prices per kWh on our Maryland electricity rates page, and expected production on our Maryland solar panels page. For state rebates, SRECs and tax exemptions, see solar incentives and rebates in Maryland.

Reading your net metering bill

Maryland solar bills usually show kWh delivered by the utility, kWh received from you, the net for the period, and your banked balance. If you buy supply from a third-party retail supplier, ask how it handles net metering credits, since the supply portion may appear on a separate line. Our explainer on how net metering works walks through common bill terms.

Next steps

If you are planning a Maryland system, ask each installer when they expect to file your interconnection application and reach permission to operate. Then compare offers with our solar quote checker before the July 1, 2027 deadline gets close.

Frequently asked questions

Is net metering ending in Maryland?

For new customers, yes. Under the Utility RELIEF Act of 2026, the standard net metering contract is available until July 1, 2027, or until 3,000 MW statewide if that comes first, and a successor program begins July 1, 2027.

Will I lose net metering if I already have solar in Maryland?

No. Customers under a net metering contract on July 1, 2027 stay eligible until an event such as decommissioning, adding capacity, a new interconnection agreement or repowering.

How are excess solar credits paid out in Maryland?

If you choose annual payout, the utility pays leftover credits after the 12-month period ending in April, at the generation or commodity portion of the rate averaged over 12 months. You can instead elect to accrue credits indefinitely.

How big can my solar system be under Maryland net metering?

Up to 2 MW, and sized to produce no more than 200% of your annual baseline electricity use.

What will Maryland's successor net metering program pay?

As of November 2026 no credit value had been approved. The PSC must approve the program framework by February 1, 2027.

Sources

Related guides

Questions and comments

Be the first to ask a question or share your experience.

Comments are checked before they appear. No links or advertising. Guidelines.

Calculators for this topic

More incentives & policy guides

All incentives & policy guides →